The
Panama Canal Expansion is moving forward to
reach its goal of bolstering the waterway’s
capacity in order to provide a better service to
customers. To date, the program is 50 percent
complete.
“The program continues to progress and reach
milestones while we focus the next phases on
building the locks,” said Panama Canal
Administrator Jorge L. Quijano.
Beginning 2013, the Expansion Program has
completed several projects.
Dredging of the navigational channels has been
completed. This included both Canal entrances,
on the Pacific and Atlantic sides, as well as
Gaillard Cut. The remaining dredging work to be
done in Gatun Lake is expected to be completed
this year.
The excavations of the Pacific lock access
channel are 70 percent complete. This project
calls for the excavation of more than 50 million
cubic meters of materials along a 6.1 km span
and is executed in four phases. Three of the
four phases have been completed and the fourth
phase is 69 percent complete.
In addition, the first shipment of 47 valves, to
be used for the operation of the third set of
locks, arrived during the last couple of weeks.
These valves are part of the Post-Panamax locks
electromechanical system that will regulate
water flow between the chambers, the culverts
and water-saving basin conduit. A second
shipment is scheduled to arrive at the end of
January. By the end of 2013, a total of 158
valves (culvert, equalization and conduit), 84
bulkheads and 328 trash racks will have arrived
for the project. The valves where built in South
Korea by Hyundai Samho Heavy Industries
Construction of the new locks has a 37 percent
progress. The new lock complexes in the Pacific
and Atlantic sides will feature three chambers,
three water-saving basins per chamber, a lateral
filling and emptying system and rolling gates.
“We estimate based on the progress that we can
begin commercial transits mid-2015,” said the
Panama Canal Administrator.
The Panama Canal Authority is closely monitoring
progress on every component of the Expansion
Program to guarantee that contractors comply
with the quality required by each contract.
The Panama Canal Expansion Program will be the
largest project at the Canal since its original
construction and will double its capacity to
allow more traffic.